We were supposed to have left for Florida this morning, but last night our flight was cancelled. But in the end, it might have been for the best.
We had a lot of water in the basement this morning. The sump pump has been acting up. Sometimes it doesn't turn on, and sometimes it doesn't turn off (and smokes from overheating). That's obviously not very safe, so Colin spent this evening running new pipes to the outside and installing a new sump pump.
Meanwhile, Justin (who was surprised to see us) sanded the floor.
Monday, April 15, 2019
Wednesday, April 10, 2019
Wedi Board
I was a bit surprised today when Valley Floors knocked on the door to finish up the Wedi board. At their lunch break, I texted the photo above to Colin to him their progress. He called right after my text to say that he hadn't run the wire to the bathtub outlet yet. So it was my turn to do some wiring. After some drilling, and digging around in the attic, I was able to run the wire.
There is still a bit a of gap between the Wedi board and the rounded ceiling on the wall above the shower head.
Evelyn liked standing in the new shower.
Sunday, March 31, 2019
Spring Thaw
Well, we were wondering if they construction had any effect on the amount of water in our basement, and I think we received our answer this morning. We have just about the same about of water as usual. I think the addition and the drainage will help with summer thunderstorm seepage (no more water squirting out of the walls). Unfortunately there is a lot of water that comes down off the hill.
The real problem is that the hole that our sump pump tube went through to get outside is gone.
For now, the water will have to go out through the bulk head.
Saturday, March 30, 2019
Train Layout
With the dust vacuumed and the tools gone, the kids have been playing in the unfinished rooms. Evelyn wanted to work with Colin on the little table in the living room. We gave permission to Alistair to build a Lego train layout in the dining room.
Friday, March 29, 2019
Last Day of Major Work
Today was the last day of major work on the house. While we're gone over spring break, Justin is going to sand and stain the floors and install some doors upstairs. Valley Floors also has to come back and finish the shower walls. But that's about it. Justin and Keefe came to the back door to say goodbye, and it was sad to see them go. They have been great working with, and we are really happy with their work.
Obviously we have a lot that we still need to do - painting, finish carpentry, tiling, and electrical. I think that will progress much more slowly.
Thursday, March 28, 2019
New Oak Floor
The weather was lovely yesterday so the guys worked on siding and trim. Today they installed the new, beautiful oak floor.
Tuesday, March 26, 2019
Subfloor Issues and Remedies
The floor under the hardwood floor in the playroom is in bad shape. There is some rot, Justin thinks was caused by a kitchen sink (there are plumbing holes by the rotted area). There are some strange wear patterns that hint to a completely different configuration of the room. (Note that the varnish where Evelyn is standing is still intact, and the floor around it worn lower.)
The other issue is that the playroom floor and the new addition don't line up exactly. If left alone, the new plywood floor would be 1/4" lower than the addition plywood at one end and 3/4" higher at the other end. Justin decided it would best to remove the subfloor in one section to be able to create a level floor. (It was the rotten bit anyway.)
The other issue is that the playroom floor and the new addition don't line up exactly. If left alone, the new plywood floor would be 1/4" lower than the addition plywood at one end and 3/4" higher at the other end. Justin decided it would best to remove the subfloor in one section to be able to create a level floor. (It was the rotten bit anyway.)
Hello basement.
Justin had to install new sistered joists (carefully over Colin's wiring), especially near the wall because the joist is under the living room wall.
Beautifully level and all ready for new oak flooring.
Monday, March 25, 2019
New Baseboard Heaters
Today Matt Piper's apprentice installed the new baseboard heaters upstairs and downstairs. On Friday they started to install heaters downstairs that were way too tall to be compatible with the paneling that we will be installing. They were nearly eleven inches tall. At just over nine inches, these new heaters are still taller than the other ones in our house, but they will fit with the paneling.
Meanwhile, outside Justin and Keefe worked on the siding the trim.
Meanwhile, outside Justin and Keefe worked on the siding the trim.
Friday, March 22, 2019
Sanding the Drywall (with some Tool Envy)
Justin has this really cool drywall sander/vacuum that he used to sand the mud, and it didn't make much of a mess.
Alyssa has tennis elbow (from downhill skiing oddly enough) so priming is going to have to wait a little bit.
Alyssa has tennis elbow (from downhill skiing oddly enough) so priming is going to have to wait a little bit.
Thursday, March 21, 2019
Siding Nearly Compete
Justin and Keefe worked some more on the siding today (before some forecasted snow tomorrow). It's just about done, and it looks great. People have asked us if we are going to keep the gray, but it's just the primer color.
Wednesday, March 20, 2019
Siding
It is amazing how the mud gets everywhere. There are globs on door frames and smears on walls.
The new wood floors came yesterday. They need to acclimatize before installation. Evelyn wants to pretend that they are stepping stones and walk from pile to pile.
Justin and Keefe worked outside yesterday today on the siding and window trim.
The new wood floors came yesterday. They need to acclimatize before installation. Evelyn wants to pretend that they are stepping stones and walk from pile to pile.
Justin and Keefe worked outside yesterday today on the siding and window trim.
This picture is from around lunchtime today (yeah sunshine!).
And here are some from the end of the day.
Monday, March 18, 2019
First Pieces of Siding
Justin finished up mudding inside, including a final coat on the corners.
Outside, they worked on the corner boards and the first pieces of siding. Looks great.
Outside, they worked on the corner boards and the first pieces of siding. Looks great.
Sunday, March 17, 2019
Birthday Dinner in the Dining Room